| August |
- Confirm first day of field work with Field Instructor by August 1
- Begin Practicum the first week of the Fall semester
|
| September |
- Learning contract due by end of third week of Fall Semester
|
| October |
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| December |
- Evaluations due by the end of the semester via IPT
- Practicum Director or Faculty Liaison may contact or meet with student and Field Instructor
- Semester break - students not in field work for approximately three weeks
|
| January |
- Begin field work II starting the first week of Spring semester
- Revised Learning Contracts due (via IPT) by the end of the first week of Spring semester
|
| February |
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| March |
- Mid-term - Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| March/April |
- Spring break - students not in field work
|
| May |
- End of semester
- Evaluations due by the end of the semester via IPT
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| August |
- Attend new student orientation
- Practicum Placement Applications due by end of month via IPT
- Set interview with Practicum Director
- Set initial interviews with agency Field Instructors
|
| September |
- Finalize placement for foundation practicum
- Confirm first day of field work with Field Instructor by end of month
|
| October |
- Begin Practicum the fifth week of the Fall semester
- Learning contract due by end of third week of practicum
|
| November |
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| December |
- Semester break - students not in field work for approximately three weeks
|
| January |
- Continue field work starting the first week of Spring semester
|
| March/April |
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
- Spring break - students not in field work
|
| May |
- End of semester
- Evaluations due by the end of the semester via IPT
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| February |
|
| March |
- Set interview with Practicum Director
- Set initial interviews with agency Field Instructors
|
| April |
- Finalize placement for Fall semester
|
| August |
- Confirm first day of field work with Field Instructor by August 1
- Begin Practicum the first week of the Fall semester
|
| September |
- Learning contract due by end of third week of Fall Semester
|
| October |
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| December |
- Evaluations due by the end of the semester via IPT
- Practicum Director or Faculty Liaison may contact or meet with student and Field Instructor
- Semester break - students not in field work for approximately three weeks
|
| January |
- Begin field work II starting the first week of Spring semester
- Revised Learning Contracts due (via IPT) by the end of the first week of Spring semester
|
| February |
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| March |
- Mid-term - Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| March/April |
- Spring break - students not in field work
|
| May |
- End of semester
- Evaluations due by the end of the semester via IPT
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| February |
- If possible, attend Agency Field Fair
|
| March |
- Set interview with Practicum Director
- Set initial interviews with agency Field Instructors
|
| April |
- Finalize placement for Fall semester
|
| August |
- Confirm first day of field work with Field Instructor by August 1
- Begin practicum the first week of the Fall semester
|
| September |
- Learning contract due by end of third week of Fall Semester
|
| October |
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| December |
- Evaluations due by the end of the semester via IPT
- Practicum Director or Faculty Liaison may contact or meet with student and Field Instructor
- Semester break - students not in field work for approximately three weeks
|
| January |
- Begin field work II starting the first week of Spring semester
- Revised Learning Contracts due (via IPT) by the end of the first week of Spring semester
|
| February |
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| March |
- Mid-term - Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|
| March/April |
- Spring break - students not in field work
|
| May |
- End of semester
- Evaluations due by the end of the semester via IPT
- Practicum Director or Faculty Liaison meets with student and Field Instructor to evaluate performance and progress
|