The following is a summary go projects affecting campus infrastructure in the fall of 2026. There are also updates on a number of recently completed projects.
Current projects
Quad utility tunnels
Work on Boise State’s steam tunnel system, the most visible and enduring project on campus, continues to progress on schedule.
Phase two is wrapping up this fall, and crews will temporarily remove fencing from the Quad for the winter. New sod and other restoration efforts will begin as the teams prepare to step away from the area for a few months.
The project’s third and final phase will resume in spring 2027, with full completion targeted for November 2027. This last phase will address areas that have yet to be replaced and the outline of construction fencing will shift accordingly.
Heating impacts to some buildings
Steam service was restored to main campus the week of Oct. 5, 2026, but eight buildings remain isolated from the system and without steam heat. These buildings are expected to be back online Oct. 20, but it may take a few days to reach full heating capacity.
The affected buildings are:
- Morrison Center (utilizing geothermal heating)
- Multipurpose Classroom Building (utilizing geothermal heating)
- Education Building
- Science Building
- SMASH (Simplot/Micron Advising and Success Hub)
- Riverfront Hall
- West Library
- North Greenhouse
Education Building elevator restoration and HVAC overhaul
Boise State is investing in this legacy building with major projects that will improve critical infrastructure for decades to come.
- Work on the elevators in the Education Building began in mid-September and will continue through May 2027. Only one elevator will be offline at a time, allowing for traffic to flow on the remaining two elevators. Consider taking the stairs, if able, during peak class change periods to avoid delays.
- A full HVAC comprehensive upgrade is planned for late spring through summer 2027. While this is a necessary upgrade, it will require the building to be fully vacated during this time. Teams are working closely with the Registrar’s office to relocate classes and staff to minimize the disruption from this project.
Completed projects
A number of projects have recently wrapped up, improving spaces across campus for students, faculty and staff:
- SUB dining area — Renovated dining space in the Westmark Student Union Building is complete and open, offering an improved experience for the campus community.
- Morrison Center restroom upgrades — Restroom renovations at the Morrison Center are finished, enhancing accessibility, capacity and comfort for patrons and performers alike.
- Hemingway Center mobility hub — The new mobility hub is complete, supporting safer, more accessible transportation options across campus.
- Greenbelt improvements— The Boise Greenbelt improvement project between Friendship Bridge and Broadway Bridge is complete, delivering a safer, improved experience along this key corridor for the Boise State and broader Boise community.
- West Stadium Lot — Improvements to the West Stadium parking lot are finished and the lot is open for use.
- Friendship Bridge and Chrisway Annex landscaping — Landscaping enhancements near Friendship Bridge and the Chrisway Annex are complete, adding to the beauty and functionality of these campus spaces.
Campus Operations wishes to thank everyone across campus for their continued patience with investing in the long-term reliability, safety and experience of Boise State’s facilities.
Questions or concerns about any of these projects can be directed to Campus Operations or submitted through the Occupant Concerns Form on the Capital Renewal website. The Current Project Hub also offers updates about these and other projects.