Boise State’s Campus Operations continues to progress on four major campus improvement projects.
Utility tunnel work will pause for winter
Work on Boise State’s steam tunnel replacement continues to progress, and crews are now preparing for a seasonal pause. Over the coming weeks, all fencing in the Quad will be removed as this stage of construction wraps up. Crews are busy placing new sod, pouring sidewalks and refreshing the area for winter, which will restore open, direct walking routes across campus.
This pause sets the stage for the project’s third and final phase, which will resume in spring 2027 and target full completion in November 2027. That final phase will address the remaining sections of tunnel not yet replaced, so when fencing returns next spring, we can expect a different layout than this year’s route.
This work is a once-in-a-generation investment in the pipes that heat and cool buildings across campus, and we appreciate the patience of the entire Boise State community as we finish the job.
Site prep begins for new Science Research Building
You may start noticing activity on the site of the future Science Research Building at the corners of Euclid, Belmont and Grant avenues in late December. This early work includes geotechnical testing, utility locates and site staging and is the first visible step toward the project’s Spring 2027 groundbreaking.
What to expect:
- Survey crews, soil borings and utility verification work in and around the site
- Fencing and equipment staging as the area is prepped
- Occasional short-term lane or walkway shifts near the site — signage will mark any detours
- Some noise and truck traffic during work hours
This groundwork follows the project’s design development milestone and the site plan submission to the City of Boise this past September. It sets the stage for full construction to begin next spring, with the building slated to open in Fall 2029.
Education Building elevator restoration and HVAC overhaul
Boise State is investing in this legacy building with major projects that will improve critical infrastructure for decades to come.
- Work on the elevators in the Education Building will continue through May 2027. Keep in mind that only one elevator will be offline at a time, allowing for traffic to flow on the remaining two elevators. Consider taking the stairs, if you are able, during peak class change periods to avoid delays.
- Preparations are underway for the comprehensive HVAC upgrade planned for late spring through summer 2027. Throughout January and February 2027, contractors will be replacing thermostats and other control systems in preparation for the full HVAC upgrade over the summer. Some of this work will be disruptive and restrict air flow requiring temporary classroom and office reassignments during this time. AES teams are working with the Registrar’s office to ensure disruptions are minimal.
Leatherman Peak Building modification set to begin in December
The Leatherman Peak Building is located in the south campus and is at the core of the Facilities Operations and Maintenance department. This building will undergo an interior improvement to expand the available office space, starting in early December through Fall 2027. You can expect construction activity, fencing and temporary sidewalk and road restrictions along Belmont between Euclid and Manitou Avenues.
Questions about campus construction?
Questions or concerns about any of these projects can be directed to Campus Operations or submitted through the Occupant Concerns Form on the Capital Renewal website. You can also visit the Current Project Hub for updates about these and other projects.
Campus Operations thanks the campus community for their continued patience as the long-term reliability, safety and experience of Boise State’s facilities improves.