Parking Advisory – Lincoln Garage Maintenance

July 31 – August 3, 2019

The parking stall lines inside of the Lincoln Garage are scheduled to be repainted starting Wednesday, July 31, 2019 with work to be completed by August 3, 2019.

While the stalls are being painted, the garage will remain open but specific sections will be closed while the work in that area is completed. Work will begin on the top floors of the garage and will progress downward according to the following schedule.

Wednesday, July 31: 5th and 4th floors closed

Thursday, August 1:  3rd and 2nd floors closed

Friday, August 2: 1st floor closed

While maintenance is in progress, signage, barricades, and flagging will designate what area of parking will be closed down and during what times. If your vehicle is parked in the Lincoln Garage while painting is occurring, please be aware of the closures and park only in a section of the garage that is open.