Skip to main content

Seth Mackley, Connor Eastwick, Adrian Marquez, Dr. Kirsten Davis

Seth Mackley's Golden Gate Bridge research poster

Introduction

Golden Gate bridge under construction, photo
  • The Golden Gate Bridge is a suspension bridge spanning the Golden Gate, the one-mile-wide strait connecting San Francisco Bay and the Pacific Ocean.
  • Golden Gate Bridge is 1.7 miles long and 90 feet wide.

The Project Construction Summary

  • The job went to a Chicago-based engineer named Joseph Strauss, who thought he could complete the project for $25 to $30 million. The actual total cost was $33 million.

Main Contractors on the Project

  • Marin and San Francisco Tower Piers: Pacific Bridge Company
  • Anchorages and Approach Piers: Barrett & Hilp
  • Structural Steel of Suspension Span and Towers: McClintic-Marshall Corporation
  • Main Cables: John A. Roebling
  • Structural Steel of Approaches: J.H. Pomeroy & Company, and Raymond Concrete Pile Company
  • Presidio Approach Road (Doyle Drive): Eaton & Smith Construction Company
  • Pavement for Suspension Spans and Approaches: Pacific Bridge Company and Barrett & Hilp
  • Electrical Work: Alta Electric & Mechanical Company

New Technology Development

Golden Gate Bridge, photo
  • Use of a $130,000 safety net from pylon to pylon; made of manila rope, 3/8 in. diameter and 6 in. square mesh that reached ten feet outside the trusses on both sides.
  • The Golden Gate was not the first job to feature hard hats and safety lines, but it was the first to enforce their use with the threat of terminating employment.
  • Glare-free goggles to enhance visibility and ward off “snow blindness” caused by the sun reflecting off the water.

Maintenance and Updates

  • Painting the bridge is an ongoing job because it is important to protecting it from harsh salt winds.
  • 13 iron workers, 3 pusher iron workers, 28 painters, 5 painter laborers, and a chief bridge painter all work on the bridge full time.
  • For nearly 30 years workers removed lead based paint from the entire bridge.
  • It costs about $65 million to maintain the bridge every year.
  • After the Loma Prieta earthquake it was determined the bridge needed a three phase seismic retrofit that is still going on today.

Fun Facts

  • Its 4,200-foot main span between the two towers was the longest for a suspension bridge until 1981.
  • The Golden Gate Bridge withstood the destructive Loma Prieta earthquake of 1989, and was closed to traffic only three times in its first 75 years due to weather conditions.
  • It was designed as a bending bridge capable of 21 foot sway and a 10 foot sag and can support the weight of bumper to bumper cars and trucks in all six lanes and pedestrians packed on the walkways.
  • The current color of the bridge, which is called international orange,was supposed to only be a primer and not the permanent color.
  • In 1937 it cost $0.50 to cross the bridge each way, which is equivalent to $18 today.

Timeline of Construction

  • January 5, 1933: Construction officially started.
  • January 1933 to February 1936: Marin and San Francisco anchorages and associated pylons.
  • January 1933- May 1935: San Francisco anchorage.
  • January 1933- June 1933: Marin pier.
  • January 1933- June 1935: Marin anchorage.
  • February 1933: Work began on the east approach road from San Francisco that extended through the Presidio to the south end of the Golden Gate Bridge.
  • March 1933: Steel for the San Francisco and Marin towers that was prefabricated brought to CA where it was stored until the Marin pier was completed and ready for tower erection.
  • March 1933- March 1934: San Francisco tower access trestle was constructed extending 1100 feet offshore.
  • November 7, 1933: Marin tower construction started.
  • October 24, 1934: San Francisco fender wall completed.
  • November 27, 1934: San Francisco pier area within the fender wall was un-watered.
  • January 3, 1935: San Francisco pier reached its final height of 44 feet above the water.
  • January 1935- June 28, 1935: San Francisco tower construction.
  • August 2, 1935- September 27, 1935: Harbor Tug and Barge Company strung the first wire cables to support the foot walks across the Golden Gate Strait in preparation for main cable spinning.
  • October 1935- May 1936: Main cable spinning and compression.
  • April 1936: Start of the Sausalito lateral approach road which was constructed as a W.P.A. project.
  • July 1936- December 14, 1936: Suspended structure.
  • July 21, 1936: Start of San Francisco approach viaduct structures and Fort Point arch construction.
  • November 18, 1936: Two sections of the Bridge’s main span were joined in the middle.
  • January 19, 1937- April 19, 1937: Roadway completed.