OIT’s Project Management Office supports technology initiatives of all types across the University. We also work closely with the Enterprise Project Management Office (EPMO) to further support Boise State’s strategic initiatives.
Complete one of the forms below to start a request. If you aren’t sure which form to use, choose the closest fit for your project. We will route the request appropriately.
July: New Fiscal Year Begins. The revised multi-year OIT Project Roadmap is published to campus. August: Break. Pause on ITPC meetings and new activities. PMO reviews the roster and briefs any new committee members. September:Review and Rebalancing. Review and celebrate the value realized from the projects completed in the past 12 months. Review active projects that are failing or no longer relevant; ITPC recommends to the Board whether to pivot, persevere, or cancel.
Call for projects and planning
Focus: Understanding the demand for new projects.
October:Annual “Call for Projects” Opens. Formal announcement to divisions and colleges to submit large IT project requests for the next fiscal year or beyond. November: Build Value Case. PMO collaborates with requesters to complete project discovery (develop business cases, technical reviews, security checks, and cost estimates). December: Break. Continue discovery activities. Pause on ITPC meetings and new activities during the end of term and holiday break.
Prioritization and vetting
Focus: Setting the stage for the upcoming year.
January:Project Intake Deadline.Final call for project requests. Finalize discovery activities. Begin sharing the available portfolio of project discovery information, sizing, and prioritization scoring with ITPC. February: Project Vetting. PMO finalizes prioritization and draft project roadmap. ITPC begins the project roadmap review and feedback process, analyzing the draft project prioritization for the upcoming fiscal year, March:Prioritization Workshop.ITPC continues to refine the project roadmap, considering dependencies, constraints, overlap, budget requests, and resourcing.
Budget alignment and finalization
Focus: Executive approvals and securing funding.
April: Final Roadmap Approval. ITPC approves the final project prioritization and roadmap for the new fiscal year in preparation for presentation to the IT Governance Board. May: Budget Sync. The CIO and OIT Advisory Group meet with the CFO to confirm the prioritized project list aligns with the University’s budget requests. June: Presentation to the Board. The project roadmap is presented to the IT Governance Board for input and approval. The PMO notifies requesters of their project status (approved, deferred, or declined).